Get help now
  • Pages 3
  • Words 726
  • Views 511
  • Download

    Cite

    Faith
    Verified writer
    Rating
    • rating star
    • rating star
    • rating star
    • rating star
    • rating star
    • 4.7/5
    Delivery result 4 hours
    Customers reviews 348
    Hire Writer
    +123 relevant experts are online

    Introduction to Structural Design Essay

    Academic anxiety?

    Get original paper in 3 hours and nail the task

    Get help now

    124 experts online

    The majority of the blame for this disaster was placed squarely on the shoulders of the design engineers and architects who overlooked vital miscalculations and failed to fix design flaws when they started to appear. Kamikaze 220) In 1970, Vincent Killing agreed to be the architect for the project. He hired Frail, Bulb, and Wesleyan, Engineers for the structural design. Construction on the Hartford Civic Center project started in 1972 with the plan to build an arena with a 2. 4 acre, state- of-the-art, space frame roof. The proposed roof consisted of offset upper and lower grids made from horizontal steel members that were connected every thirty feet by steel diagonal members.

    The upper horizontal members were braced by additional steel diagonals, and the main diagonals were braced at their mid-points by horizontal steel bars (Doris 284). The roof frame was completely assembled on the ground and inspected before it was lifted into its final position. Upon inspection, excessive deflections in some of the nodes were found. The engineers were notified, but nothing was done to fix the problem. The roof was lifted into position and deflection was measured to be twice that predicted by computer analysis.

    The engineer’s response to this was that such discrepancies between actual and theoretical were normal and should be expected. When the subcontractor began fitting the steel frame supports for fascia panels on the outside of the truss he ran into great difficulties due to excessive deflections of the frame. Upon notification of this problem, the general contractor “directed the subcontractor to deal with the problem or be responsible for delays. ” (ENRON, April 6, 1978). The roof was completed on January 16, 1973. Why was this roof unable to hold up in a snowstorm?

    When the individual top chord members of the truss, or frame, began to buckle due to the stress on the roof from the weight of the snow and ice, the load that those members carried was distributed to adjoining top chord members. The adjoining members, unable to handle the added weight also began to buckle, which in turn caused the lower chord members to suckle bringing the whole roof down to the arena below (Doris 284). Buckling is the sudden uncontrolled lateral displacement of a column, at which point no additional load can be supported.

    The sideways deflection or buckle will eventually fail in bending if loads are increased. Long slender columns are prone to fail by buckling- a function of the column’s dimensions and its modulus of elasticity (Mooneye 342). The reasons and theories as to why the roof collapsed can be found in the work of the design engineers, architects, construction managers, and city officials. The engineers depended on computer analysis to assess the safety of their design.

    The roof design was extremely susceptible to buckling a mode of failure not considered by the Due to the construction manager’s refusal to hire a structural engineer for the purpose of inspection, no one realized the structural implications of the bowing structures. Finally, the Hartford Department of Licenses and Inspection did not require a peer review of the arena design. If a second opinion had been required the design deficiencies responsible for the arena’s collapse probably would have been covered (Fell and Carper, 1997).

    In researching this project a lot of what I found blamed the engineers for relying on computer analysis to assess the safety of their design. This assignment was to investigate the constructor’s role so I want to talk about that a little bit. After learning about how this project failed I realized how important it is for construction managers to have a basic understanding of structural design. Had the construction manager on this Hartford Civic Center Job understood the need for a structural engineer I might not be writing this paper.

    How he overlooked the deflection is shocking, that is a huge red light to get some structural help, especially on a Job of this magnitude. In looking at the construction process a little broader than that of the construction manager; everyone involved, from the architect and engineer, to the sub-contractors doing the labor need to group together and work as a unit so failures like this don’t occur. It seems like there was a huge lack of communication between parties involved. Communication is a huge part of achieving and accomplishing a project successfully.

    This cannot happen or problems ND failures like this will occur.

    This essay was written by a fellow student. You may use it as a guide or sample for writing your own paper, but remember to cite it correctly. Don’t submit it as your own as it will be considered plagiarism.

    Need custom essay sample written special for your assignment?

    Choose skilled expert on your subject and get original paper with free plagiarism report

    Order custom paper Without paying upfront

    Introduction to Structural Design Essay. (2017, Sep 06). Retrieved from https://artscolumbia.org/introduction-structural-design-19692/

    We use cookies to give you the best experience possible. By continuing we’ll assume you’re on board with our cookie policy

    Hi, my name is Amy 👋

    In case you can't find a relevant example, our professional writers are ready to help you write a unique paper. Just talk to our smart assistant Amy and she'll connect you with the best match.

    Get help with your paper